Carrefour and CDB Fire Station Facilities

Build

Project Description

PED CONCEPTS was contracted to provide turn-key services to execute two (2) Fire Station Construction projects to accommodate the need of the host nation at both sites, Carrefour and Croix De Bouquets. Work included but was not limited to metal building installation, parking areas, the site layout of the building and the proposed vehicular parking spots design, ground conditions, fittings, fixtures and finishes, mechanical, electrical, and plumbing, and HVAC design and installation and complete self-sufficient potable water systems. PED CONCEPTS GROUP worked closely with the local Embassy, NAVFAC SE staff, and the Subcontractor to execute the VAT and permits for the local requirements on-site.

Project Details

Client: Carrefour and CDB, Haiti

Agency: NAVFAC SE, SOUTHCOM

Project Value: $1,611,706